Lakeview Addition Zoning Public Hearing for Lots 7 and 8 in Block 1, and Lots 13-24 in Block 2: Public Notice for the City of Shallowater   The City of Shallowater would like to give all interested parties the right to appear and be heard at the council meeting on Tuesday, the 16th of February 2021 at 7:00 p.m. in the Police Department Training Room, 607 Ave G, Shallowater, Texas on the issue of zoning for the territory described, to wit:  A 2.24977 acre tract of land of a tract recorded in County Clerk File Number (CCFM) 2012040349, Official Public Records of Lubbock, County, Texas as  described in Volume 588, Page 384, Deed Records of Lubbock County, Texas, and described as Lakeview Addition; Lots 7 and 8, Block 1 and Lots 13-24, Block 2.  The property is located south of 5th Street and west of Avenue H. The City of Shallowater proposes to institute R-2 (Multi-Family Residential, duplexes) zoning for the 2.2497 acre tract of land in Lakeview Addition: Lots 7 and 8, Block 1 and Lots 13-24, Block 2.  Any questions or concerns may be directed to City Hall, 806-832-4521 or 806-696-4300.  Thank you

Weather in Shallowater

Construction begins 9/8/2020 for the 10th Street Reconstruction and Drainage Improvement Project

City of Shallowater Notice

Construction will begin on the 700 feet of 10th Street closest to Avenue Q on Tuesday, September 8, 2020.  The city will also be improving the drainage along Avenue Q and the alleys from 10th Street to 7th Street.  The anticipated schedule for the street work is through the end of September. 

There will be no through traffic on 10th Street.  Residents will have access to their homes, but will need to enter and leave on Avenue N instead of Avenue Q.  There will be through traffic both directions on Avenue Q, but it will be slowed down.

Bus traffic will need to be diverted to 9th Street.  When the construction begins on the approaches traffic will be limited to one lane on 7th, 9th, and 10th Streets.

The city will be coordinating garbage pick up with South Plains Waste Services to ensure minimal disruption of services. 

Planned Phasing Schedule:

September 9-11    Mix 10th Street and proof roll subgrade

September 9-14    1st half of the 7th and 9th Street approaches

September 11-14 –  Mix in cement for cement stabilized base. 

September 15-16 –  Paving of 10th Street

September 15-18 –  1st half of 10th Street approach

September 18-22 –  2nd half of 7th and 9th Street approaches

September 23-25 –  2nd half of 10th Street approach

*Phasing shifts will take place during the curing process and all valley gutters will be completed during the work in those particular areas. 

 

Please be patient during the construction of this project.  This work is needed and the finished product will be worth it. 

 

If you have any questions please do not hesitate to contact City Hall at 806-832-4521.

 

Pavecon Ltd. will be as accommodating as possible to the residents on 10th Street.  They will stop equipment and direct you into your driveways.  If you have a rear drive, please use it.  If you have the ability to walk, parking closer to the west end of the street would be helpful.  Pavecon has provided two contacts:

Cory Sandefer, Division Manager          806-412-9050

Sean Moore, Senior Project Manager  806-317-4529